A general shutdown procedure is as follows:

  1. Turn off either the “Solar Supply Main Switch” located in the Switchboard or the “AC ISOLATOR” adjacent/below the inverter.
  2. Turn off all ‘PV ARRAY DC ISOLATOR(S)” located adjacent/below the inverter.

WARNING: DO NOT OPEN PLUG AND SOCKET CONNECTS OR PV STRING ISOLATORS WHILE THE SYSTEM IS UNDER LOAD

Start-up Procedure is the reverse of the Shutdown Procedure.